Design for spillway replacement at Bond Falls Dam

About this project

client
Upper Peninsula Power Company
location
Michigan
cost
$5-10 million
completion date
2011

A spillway capacity study revealed that the Bond Falls reservoir, constructed in the 1930s, had insufficient capacity to pass probable maximum flood (PMF) flows. The reservoir was drawn down to lower the risk of flooding in event the dam’s PMF level was exceeded during a storm. To meet Federal Energy Regulatory Commission (FERC) dam safety criteria, the dam needed a new spillway sized to pass a PMF event.

Barr developed a detailed design based on a physical scale-model study configuration tested by St. Anthony Falls Laboratory. The design consisted of two new gates, wider and higher than the original single gate. A new minimum flow pipe was also designed integral with the new concrete spillway structure to provide minimum discharge flows to the downstream river channel.

Our design included a staged cofferdam to minimize reservoir drawdown and provide a dry, stable work area for demolition and construction activities. Barr developed a water management strategy to stage the cofferdam sequencing to accommodate construction and maintain continuous minimum flows to the downstream river channel throughout construction.

The new spillway consists of the following features:

  • Two tainter-gate bays, each larger than the original bay

  • Replacement of the 35-foot-high earth embankment and steel sheet-pile seepage-cutoff walls

  • Remote tainter-gate monitoring and operation

  • An emergency generator in the control building, capable of powering one gate hoist

  • A new minimum-flow structure to provide flexibility in flow discharge location

  • Monitoring equipment to accurately measure discharge flows and reservoir levels

  • Raised embankment crests to address low points on the main and perimeter dam locations

Barr’s work also included documenting a mini–potential-failure-mode analysis (PFMA) conducted to identify potential failure modes, fatal flaws, and critical design issues to be addressed during development of a final design. The mini-PFMA served to supplement a previous PFMA, adding failure modes applicable during construction of the replacement spillway.

The completed Bond Falls spillway can now accommodate twice as much discharge as the preconstruction configuration. Barr also developed a commissioning and refill plan to foster safe, controlled startup and fill conditions.

Key team members

Mark Kretschmer

Vice President
Senior Civil Engineer

Brian Tri

Vice President
Senior Civil/Structural Engineer

Bill Forsmark

Vice President
Chief Marketing Officer

Related Hydro projects

Landfill-gas monitoring at remediated dump to support brownfield redevelopment
Air dispersion modeling for distributed-generation plant
Landscape master plan for watershed district
O&M manual for green-infrastructure stormwater BMPs
Third-party transmission-line construction monitoring
Design of abutment wall extension at Dells hydro station
Design and prioritization of spillway gate repairs
Engineering design for HDD pipeline replacement under highway
Incident energy and arc flash hazard analyses of three facilities
Natural-resources management plan for suburban park
Feasibility design and inspections of an urban stormwater-management tunnel
Engineering services and permitting assistance for Bison 2 and 3 wind farms
Dam safety consultations for SaskPower
Geotechnical, structural, and civil work for Canadian wind farm
Electric-energy resource options study
Design services for solar generation facility
Mine closure and reclamation
Monitoring of constructed wetland for groundwater remediation
Study of engineering risks and site feasibility for windpower client
Stormwater storage facility for major Minneapolis interstate artery
Water-quality and sediment-dredging study to restore a phosphorus-impaired lake
Environmental review for proposed natural-gas pipeline
Waste-gas scrubber design engineering for taconite pellet plant
EMIS implementation and related assistance
Installation of new auxiliary boilers for power plant
Inspection and repair of urban stormwater tunnels
Responding to wind-farm tornado damage
Bridge movement monitoring
Evaluation of wind-turbine foundation following fire damage
Engine compliance tool update
Natural resources master plan
Embankment stabilization along Highway 73
Test burn for cofiring coal and biomass
Transmission line EIS
Flood forecast mapping for city's emergency response and planning efforts
Air-quality permitting and compliance support at pipeline terminals
Environmental permitting and compliance support at terminals
Improvements to municipal flood-risk-protection system
Monitoring and maintenance of remediation system at wood-treating site
Groundwater-surface water study of McKenna Lake
Permitting and wetland delineation for a community solar garden
Highway 55 storm-tunnel inspection
Penstock replacement at McClure Dam
Highwall stability assessment
Options study and design to restore biomass fuel-handling system
Infrastructure inspection program for Minnesota watershed district
Air permit-to-install strategy and application
Steam-line evaluation at Rapids Energy Center
Air quality permitting for distributed-generation plant
GHG compliance monitoring for oil sands facility
Air-quality-permitting support for refinery assets
Site reviews for solar gardens across Minnesota
Whitewater State Park stream restoration
Hennepin County sustainable landscape guidelines
Spillway design for iron-ore-mining and mineral-processing facility
Water quality and ecological improvements to an urban lake
Groundwater compliance assistance for CCR Rule
Developing health assessment tools for wind-turbine towers and foundations
Hydrology and hydraulic modeling of a tunnel system
Condition assessment and options study for hydro facility
Floodproofing of utility switchyard
Concept-level design of wastewater discharge option
Vapor-mitigation implementation and maintenance at business center
Environmental review and permitting for natural-gas-distribution projects
Minnehaha Park lower glen restoration
Design of an LED lighting system for a downtown streetscape
Fast-track realignment of a storm sewer
Environmental review for peaking plants
Municipal drinking-water wellhouse evaluation and design
Engineering and design services for new truck dumper
Restoration of trout habitat in Vermilion River
Solar-energy-system compliance
Auxiliary boiler installation
Remedial investigation, negotiation, and design for Superfund site
Stormwater-development reviews for an urban watershed district
Retrofit engineering for ash conveyance
Energy integration study for waste-heat utilization
Environmental services for coal-yard decommissioning
Option study and design for air jig dewatering system
Permitting, design, and construction oversight for CCR surface impoundment
Groundwater modeling for water-supply wellfield expansion
Transmission-line permitting assistance
Structural and electrical engineering for coal-dryer load-out improvements
Environmental review for natural gas pipelines
Poplar Bluff substation upgrade
Transmission line upgrades for reliable power delivery
arc-flash analysis at Coal Creek Station
Study of solar developments on closed Minnesota landfills
Geotechnical investigation for the East Valley Battery Storage Facility
Geotechnical investigation of pumped-storage hydroelectric facility
Preliminary geotechnical engineering and geophysical investigation
Willow River Dam rock arch rapids design services
Seneca solar project geotechnical engineering services
Conceptual development for Coal FIRST initiative
Pre-FEED study for Coal FIRST initiative
Civil engineering services for 10 MW solar facility
Structural analysis and evaluation of powerhouse
Permitting assistance for partial repowering of wind facility
Environmental review and permitting for windfarm repowering
Mitigation of aerosol impacts from coal combustion
Spillway redesign at Cedar Falls Hydro Generating Station
Air-quality services for steel company
Hydropower facility evaluation and improvement recommendations
PMF modifications at hydroelectric plants
Hastings levee certification
Crane walk geotechnical engineering at Kings Point wind site
PMF study for the Dead River
Analysis of microbial ecology in selenium bioreactor
Statistical analysis of coal-silo vibrations
Cyclic degradation geotechnical evaluation for wind turbine foundations
Upgrades to mineral processing plant
Calculating stormwater fees via remote-sensing technology
PFAS treatment during power plant decommissioning
Gate upgrade at Island Lake Dam
Acid-generating rock identification and mitigation
Solar on reclaimed coal mine, settlement and subsidence risk analysis
Blaine water treatment plant 4
Permitting and nondegradation services for sugar-beet facility
Cathodic protection design for pipeline projects
Grassy Point and Kingsbury Bay habitat restoration
Engineering and design for the rehabilitation of Karey Dam
Tailings dam safety inventory and semiquantitative risk analysis
Park and water-feature evaluation and renovation
Rock-fall protections at Interstate State Park
Air permitting assistance for manufacturing coating facility
Redesign and optimization of crystallizer piping
Environmental support for solar power facilities
Desktop study and geotechnical investigation for new wind power site
Permitting and field review for natural gas pipeline replacement
Wind farm repowering structural assessment
Renewable energy development plan
Multi-phase levee alterations for the City of Des Moines, Iowa
Carbon-capture-system feasibility study
Third-party dam safety review of tailings-storage facility
Implementing a dual fuel system for peaking plant
Environmental planning and permitting for solar-generation and battery-storage project