Fall 2022
Stabilizing a community's backup water supply In southwestern Wyoming, a storage failure threatened residents’ backup water supply. Below, learn how Barr and our project partners remedied a reservoir dam and levee.

Stabilizing a community's backup water supply

In Wyoming’s Sweetwater County, the Joint Powers Water Board manages the treatment and supply of drinking water, all of which is drawn from the Green River. Although the river generally provides enough water for county residents, its quality drops when spring runoff or heavy rainfall washes soil and debris into the river. Historically, during those periods the Green River water treatment plant sometimes had difficulty meeting demand.

In response, the board decided to build a dam and levee to create an off-channel reservoir that would hold additional river water and allow suspended solids to settle out of it before treatment. The solution would also provide an emergency water source if contaminants or other harmful substances were found in the river.

Construction was nearly complete when a leak test revealed that almost five times more water than expected—hundreds of gallons a minute—was seeping into the earth. In addition, the levee was slowly sinking into the ground, and the soil-cement reservoir lining was rapidly deteriorating. The board solicited bids for a team to design and implement repairs and finish the storage project.

Barr and our project partners, Freese and Nichols and JFC Engineers and Surveyors, were selected for the work. After inspecting the reservoir lining, dam, and levee, our team developed a remediation plan that included adding a concrete leveling surface to the soil-cement steps on the dam face, building an internal earthen buttress to stabilize the levee, and installing a membrane liner to minimize leakage.

Barr and our project partners developed a remediation plan for a reservoir failure that threatened residents’ backup water supply.
Barr's remediation plan for the leaking reservoir included adding a concrete leveling surface to the soil-cement steps on the dam face, building an internal earthen buttress to stabilize the levee, and installing a membrane liner to minimize leakage.

The Barr team completed investigation and design and helped procure a contractor in less than a year, and construction was deemed substantially complete this spring. Sweetwater County now has a reliable alternative water source when the Green River runs muddy.

Interested in learning more about Barr's dam engineering services? Contact our team.

About the author

Jon Ausdemore has over two decades of experience as a project manager and project engineer on dam, spillway, site-development, industrial landfill, and tailings basin projects. He has been involved with nearly 100 dam projects involving safety and condition assessment inspections, design, and construction oversight and management.

 

Jon Ausdemore
Jon Ausdemore
Vice President, Senior Civil Engineer
Contact

 

In This Issue

Theme picker

Stabilizing a community's backup water supply

Stabilizing a community's backup water supply

Q&A: In your ESG journey, keep the destination in mind

Q&A: In your ESG journey, keep the destination in mind

Inflation Reduction Act opens door for energy investment

Inflation Reduction Act opens door for energy investment

Reviving landings on Lake Michigan's Plum and Pilot Islands

Reviving landings on Lake Michigan's Plum and Pilot Islands

Theme picker

Theme picker